EPA announced new guidance on New Source Review (NSR) pre-construction requirements, broadening the range of permissible activities prior to obtaining an air permit. Pre-permit activities now allowed include pouring pads and constructing building shells. Previous EPA guidance had generally limited permissible construction prior to obtaining an air permit to ordering equipment, site clearing/grading, and temporary equipment/materials storage.